Project Overview > Project Milestones
- The Board of PetroSA approved the business case for Project Mthombo in 2007.
- In 2008 HSBC was appointed as the financial advisor, KBC was appointed as the technology advisor, and KBR was appointed as an Engineering company to conduct the full feasibility and Front-end Engineering and Design (FEED)
- In October 2008 PetroSA was granted a manufacturing license by the Department of Minerals and Energy which allows PetroSA to manufacture refined petroleum products at the Coega site.
- Pre-Feasibility and Full-Feasibility Studies were completed in 2009
- In October 2009 a cooperation agreement between PetroSA and Coega Development Corporation (CDC) was signed
- The project is expected to proceed to the FEED Phase (Front End Engineering & Design) once approval has been obtained
- All aspects of Project Mthombo will be subject to a full Environmental Impact Assessment (EIA) that will commence during the FEED Phase. This phase is expected to commence during 2010 subject to approval.
- Final approval for investment, after FEED and a successful EIA, will be sought early 2012. Thereafter, construction will commence and is planned to be completed by the end of 2015. The refinery will be commissioned during 2016.
PROJECT NEWS
PetroSA and the Coega Development Corporation (CDC) sign a cooperation agreement for the planned Coega oil refinery
Read more
Viewed
PetroSA appoints distinguished legal consortium as advisors for Project Mthombo
Read more
Viewed
Major opportunities for BEE companies at Project Mthombo
Read more
Viewed